Initial tests of La Sal shaft ore in the Alkaline Leach Pilot Plant

Initial testing of La Sal ore in the Alkaline Leach Pilot Plant at Grand Junction, Colorado, took place during the period February 15 to March 7, 1955. By the use of an extended leaching time of 112 hours and a temperature of 172°F, a dissolution of 99.1 percent of the uranium was obtained. Three-st...

Full description

Main Authors: Jones, J. Q.; Skiles, D. O.; Winslow, G., National Lead Company, Inc. Raw Materials Development Laboratory
Format: Text
Language: English
eng
Published: 1955
Subjects:
Online Access: http://hdl.handle.net/11166/84691
http://archives.mountainscholar.org/cdm/ref/collection/p17393coll30/id/8491
id oai:archives.mountainscholar.org:p17393coll30-8491
recordtype dspace
spelling oai:archives.mountainscholar.org:p17393coll30-84912023-10-18 Initial tests of La Sal shaft ore in the Alkaline Leach Pilot Plant Jones, J. Q.; Skiles, D. O.; Winslow, G. National Lead Company, Inc. Raw Materials Development Laboratory Colorado Plateau 1955 July 29 1955-07-29 Initial testing of La Sal ore in the Alkaline Leach Pilot Plant at Grand Junction, Colorado, took place during the period February 15 to March 7, 1955. By the use of an extended leaching time of 112 hours and a temperature of 172°F, a dissolution of 99.1 percent of the uranium was obtained. Three-stage filtration of the pulp gave a soluble loss of 1.5 percent and a filter rate of 276 pounds per square foot per 24 hours, using 0.05 pound of Separan-2610 per ton. The best filter rate obtained was in excess of 600 pounds per square foot per 24 hours. Overall recovery of uranium in the "yellowcake" was 95.7 percent for the entire run. The product assayed 75.5 percent on a dry basis, and slightly better than 80 percent U3O8 if washed on the filter before drying. Indicated reagent consumptions are 20 pounds of caustic soda and 0.1 pound of Separan per ton of ore. Fuel oil requirements for pulp heating were 21.3 gallons per ton of ore. Contract no. AT(49-6)-924 Radioactivity; U.S. Atomic Energy Commission; Uranium ores English eng Text Atomic Energy Commission collection Atomic Energy Commission collection WIN-20 Colorado Mesa University. Tomlinson Library All written materials, drawings, maps, photographs and other graphics are property of the contributor. The copyright and related rights status of this Item has not been evaluated (https://rightsstatements.org/vocab/CNE/1.0/). Please refer to the organization that has made the Item available for more information. http://hdl.handle.net/11166/84691 http://archives.mountainscholar.org/cdm/ref/collection/p17393coll30/id/8491
institution Archival Material
collection DSpace
language English
eng
topic Radioactivity; U.S. Atomic Energy Commission; Uranium ores
spellingShingle Radioactivity; U.S. Atomic Energy Commission; Uranium ores
Jones, J. Q.; Skiles, D. O.; Winslow, G.
National Lead Company, Inc. Raw Materials Development Laboratory
Initial tests of La Sal shaft ore in the Alkaline Leach Pilot Plant
description Initial testing of La Sal ore in the Alkaline Leach Pilot Plant at Grand Junction, Colorado, took place during the period February 15 to March 7, 1955. By the use of an extended leaching time of 112 hours and a temperature of 172°F, a dissolution of 99.1 percent of the uranium was obtained. Three-stage filtration of the pulp gave a soluble loss of 1.5 percent and a filter rate of 276 pounds per square foot per 24 hours, using 0.05 pound of Separan-2610 per ton. The best filter rate obtained was in excess of 600 pounds per square foot per 24 hours. Overall recovery of uranium in the "yellowcake" was 95.7 percent for the entire run. The product assayed 75.5 percent on a dry basis, and slightly better than 80 percent U3O8 if washed on the filter before drying. Indicated reagent consumptions are 20 pounds of caustic soda and 0.1 pound of Separan per ton of ore. Fuel oil requirements for pulp heating were 21.3 gallons per ton of ore.
format Text
author Jones, J. Q.; Skiles, D. O.; Winslow, G.
National Lead Company, Inc. Raw Materials Development Laboratory
author_sort Jones, J. Q.; Skiles, D. O.; Winslow, G.
title Initial tests of La Sal shaft ore in the Alkaline Leach Pilot Plant
title_short Initial tests of La Sal shaft ore in the Alkaline Leach Pilot Plant
title_full Initial tests of La Sal shaft ore in the Alkaline Leach Pilot Plant
title_fullStr Initial tests of La Sal shaft ore in the Alkaline Leach Pilot Plant
title_full_unstemmed Initial tests of La Sal shaft ore in the Alkaline Leach Pilot Plant
title_sort initial tests of la sal shaft ore in the alkaline leach pilot plant
publishDate 1955
url http://hdl.handle.net/11166/84691
http://archives.mountainscholar.org/cdm/ref/collection/p17393coll30/id/8491
_version_ 1802128067606347776
score 13.9117775